Browse All Projects

Rehabilitation of the Joralemon Tunnel

New York, New York

Market Sector

Rail and Transit

Type

Passenger and Transit, Stations, Yards and Terminals, Systems

Services Provided

Construction Management, Construction Engineering and Inspection

Region

Americas

T.Y. Lin International (TYLI), as managing partner in a joint venture, provided Consultant Construction Management (CCM) Services to New York City Transit (NYCT) for the Joralemon Tube Rehabilitation. The project is located between Manhattan and Brooklyn in New York City and serves subway lines 4 and 5, which were damaged by the tidal surge during Superstorm Sandy. The team provided services during the pre-construction, construction, and close-out phases of the project.

Project scope comprised repairs to facilities, including fan plants, circuit breaker houses, substations, pump houses, and rehabilitation work along the 7,000-foot length of the Joralemon Tunnel. Resiliency measures, such as waterproof grouting, flood-proof doors, and protective coatings, were also incorporated.

The CCM team performed constructability reviews; provided cost-saving design solutions; reviewed the sequencing, staging and phasing requirements; and provided safety inspections during construction.

Project Highlights:

  • TYLI assisted NYCT in organizing overnight and weekend General Orders (GOs) shutdowns for inspections.
  • TYLI reviewed the contractors’ baseline schedule and updated the monthly critical path method (CPM) schedule.
Awards
Platinum Award for Special Projects, 2019
American Council of Engineering Companies of New York (ACEC-NY)