Tajo River Viaduct
Work Scope
Detailed Design and Construction Engineering
Property: Spanish Ministry of Public Works. Roads Bureau
Builder: Sacyr
Ending Year: 2015
Technical Data
Spans 1, 2 and 3: prestressed concrete box bean. Span 3: main segment with steel-concrete composite twin-girder embedded in concrete boxes at the piers
Overall length: 253.75 m
Main span: 114 m; Composite Segment 94.50 m
Span lengths: 27.75+56.25+114+55.75
Width: 11 m